A fresh government factsheet, reported on 30 October 2026, restates India’s ambition under the National Green Hydrogen Mission (NGHM): 5 million metric tonnes (MMT) a year of green hydrogen production capacity by 2030. The headline numbers are familiar, but the detail underneath — which states have actually written policy, and where certification stands — is more useful to anyone choosing a site or structuring an offtake today.
What was reported
According to Convergence Now’s summary of the official factsheet, the mission is expected to attract more than ₹8 lakh crore of investment, create over six lakh jobs, avoid roughly 50 MMT of CO₂ a year and cut cumulative fossil fuel imports by around ₹1 lakh crore by 2030.
On the state side, the picture has three tiers:
- Dedicated policies notified (6): Gujarat, Andhra Pradesh, Maharashtra, Uttar Pradesh, Rajasthan and West Bengal.
- Draft policies being finalised (4): Haryana, Punjab, Bihar and Kerala.
- Hydrogen folded into existing industrial or RE policies (5): Himachal Pradesh, Madhya Pradesh, Odisha, Telangana and Chhattisgarh.
On certification, MNRE launched the Green Hydrogen Certification Scheme in April 2025; the Bureau of Energy Efficiency (BEE) is accrediting verification agencies, and the dedicated portal went live in June 2026. Internationally, MNRE holds MoUs or joint declarations with Australia, Finland, France, Germany, Saudi Arabia, the UAE and Uzbekistan, alongside the India–US Hydrogen Task Force.
This sits alongside the latest figures on offtake: India has now secured about 5.56 lakh tonnes a year of supply commitments — roughly a tenth of the 2030 target. Our offtake commitments update looks at what that means for projects.
Engineering take
1. State policy is now a site-selection input, not a footnote
Most of a green hydrogen plant’s levelised cost sits in electricity. The value of a state policy lies in what it does to that power bill: waivers or reductions of transmission and wheeling charges, cross-subsidy surcharge and electricity duty, banking terms for open-access renewables, and land allotment near RE zones or ports. A 1 ₹/kWh swing in delivered power cost moves LCOH by roughly ₹50–55/kg at typical specific consumption of 50–55 kWh/kg. That is larger than most electrolyser-price differences between OEMs.
For developers, the six notified states are where these terms can be read, modelled and put into a financing case today. In the draft-policy states, treat incentives as upside in the base case, not as committed value. And for the five states covering hydrogen through general industrial policy, check clause-by-clause whether electrolysis load actually qualifies for RE open-access concessions — it often is not explicit.
2. Certification changes the metering and data design
With the BEE portal operating, “green” becomes something an accredited agency audits, not something a developer declares. In practice that pushes requirements back into engineering:
- Revenue-grade metering at the RE injection point, at the electrolyser rectifier input and on auxiliaries (compressors, chillers, water treatment), so emission intensity can be calculated per batch.
- Time-matched data for any grid-banked energy, since banking arrangements and the emission threshold interact.
- Hydrogen flow and purity metering at the battery limit, with calibration records an auditor can follow.
- A historian/SCADA architecture that keeps tamper-evident records for the full certification period.
Retrofitting this after FEED is costly. We recommend writing the certification data requirements into the basis of design at the concept stage.
3. Export projects need two certificates, not one
Much of the offtake India has signed is for export, mostly as green ammonia. Buyers in Japan, Korea and the EU apply their own carbon-intensity rules, which differ from the Indian threshold in system boundary, treatment of grid power and transport emissions. A plant that passes the Indian scheme comfortably can still fall short of an EU RFNBO-type test on additionality or temporal correlation. Developers should design to the stricter of the domestic and destination-market rules, and the government-to-government MoUs listed above are a reasonable starting point for mutual-recognition talks.
4. The 5 MMT gap is an execution problem
Committed offtake at about 0.56 MMT a year against a 5 MMT target leaves a lot to build in roughly four years. The binding constraints we see on Indian projects are rarely the electrolyser stack: they are RE plus storage firming, transmission connectivity, desalinated water supply at coastal sites and skilled O&M staff. Price discovery has helped — SECI tenders have produced a benchmark of around ₹279/kg (see our guide to calculating LCOH for what sits behind such numbers) — and hub-level planning, such as SECI’s detailed project reports for green hydrogen hubs, should help with shared utilities. But each project still has to close its own power, water and grid case.
Bottom line for Indian developers
Compare states on delivered power cost rather than headline incentives, build certification metering into the design from day one, and for export projects test compliance against the buyer’s rules early. If you are screening sites or preparing a pre-feasibility study, talk to Avoltium’s engineering team.