The levelised cost of hydrogen (LCOH) is the single number every Indian green hydrogen tender, bank model and offtake negotiation eventually comes down to. Yet the figures quoted in press releases are rarely comparable, because each one hides different assumptions about tariff, utilisation, financing and stack life. This guide walks through how to build an LCOH calculation properly, with a worked 100 MW example in rupees, so you can test vendor quotes and bid prices yourself.

1. The LCOH formula

LCOH is the constant price per kilogram that makes the net present value of a project zero over its life. In practice it is easiest to compute as the sum of annualised costs divided by annual production:

Advertisement
LCOH (₹/kg) = [CAPEX × CRF + Fixed O&M + Annualised stack replacement
               + Electricity cost + Water & consumables] ÷ Annual H₂ (kg)

CRF = i(1+i)^n / [(1+i)^n − 1]

Here i is the real weighted average cost of capital (WACC) and n is plant life in years. The capital recovery factor (CRF) converts an upfront investment into an equivalent annual payment. For a full-NPV model with year-by-year degradation and escalation you should still build a cash-flow sheet, but the annualised method lands within a few percent and is ideal for screening.

2. The inputs that actually matter

Installed CAPEX (system, not stack)

Vendors quote stack or “electrolyser package” prices. Your LCOH needs the full installed cost: stacks, rectifiers and transformers, gas-liquid separation and purification, water treatment, cooling, compression to the delivery pressure, controls, civil works, EPC margin and owner’s costs. On most Indian projects the stack is well under half of the installed cost. If a quote looks cheap, check which of these items it excludes. Our rectifier topology guide covers one of the larger BoP line items.

Specific energy consumption (system level)

Use system kWh/kg measured at the AC point of connection, including rectifier losses, BoP auxiliaries and compression, and averaged over the stack’s life. Beginning-of-life stack figures can be 3–6 kWh/kg better than the life-average system number. Since electricity is usually 60–70% of LCOH, this one parameter swings the result more than almost anything else.

Capacity factor and power tariff (these are linked)

In India the real design decision is the renewable supply profile. Solar-only supply gives an electrolyser capacity factor around 25%; solar-wind hybrids reach 40–55%; firmed or round-the-clock (RTC) supply with storage or grid banking pushes past 70%, but at a higher tariff. Higher utilisation spreads CAPEX over more kilograms, while a higher tariff raises the energy component. LCOH must be optimised across both together, never one at a time. Open-access charges, banking charges and the transmission waivers available to green hydrogen projects change the delivered tariff materially, so model the landed cost at the plant, not the generator’s PPA price.

WACC and plant life

A long-term offtake from a creditworthy buyer (refinery, fertiliser unit, or an export contract) can cut the cost of capital by several percentage points compared with a merchant project. That is why offtake structure is an engineering-economics input, not just a commercial one.

Stack replacement and degradation

Stacks typically last 60,000–90,000 operating hours depending on technology and duty cycle. Variable renewable operation with frequent cycling can shorten this. Model at least one replacement within a 20–25 year life, and account for rising specific energy as stacks degrade.

Water and consumables

Stoichiometric water is about 9 L per kg of H₂, but raw water intake after RO rejection, demineralisation and cooling losses is often 15–30 L/kg. The cost per kilogram is small, but water availability can decide whether you get a site at all. Use our water consumption calculator to size it.

3. Worked example: 100 MW plant in India

The numbers below are illustrative screening assumptions, not quotes. Replace them with your own project data.

InputAssumption
Electrolyser capacity100 MW (AC)
Installed system CAPEX₹6.0 crore/MW → ₹600 crore
Real WACC / life10% / 20 years
Capacity factor55% (solar-wind hybrid) → 4,818 h/yr
System specific energy (life average)53 kWh/kg
Delivered power tariff₹4.0/kWh
Fixed O&M2.5% of CAPEX per year
Stack replacementYear 10, 20% of CAPEX
Water & chemicals₹1.5/kg H₂

Step 1: Annual production

100,000 kW × 4,818 h ÷ 53 kWh/kg ≈ 9.09 million kg/yr (about 9,090 tonnes).

Step 2: Capital charge

CRF at 10% over 20 years = 0.1175. Annual capital charge = ₹600 crore × 0.1175 ≈ ₹70.5 crore. Per kg: ₹70.5 crore ÷ 9.09 million kg ≈ ₹77.5/kg.

Step 3: Electricity

53 kWh/kg × ₹4.0/kWh = ₹212/kg.

Step 4: O&M, stack replacement and water

Fixed O&M: ₹15 crore/yr ÷ 9.09 million kg ≈ ₹16.5/kg. Stack replacement: ₹120 crore in year 10 has a present value of about ₹46.3 crore; annualised with the CRF that is ₹5.4 crore/yr, or about ₹6.0/kg. Water and chemicals: ₹1.5/kg.

Result

Component₹/kgShare
Electricity212.068%
Capital recovery77.525%
Fixed O&M16.55%
Stack replacement6.02%
Water & chemicals1.5<1%
LCOH≈ 313.5100%

For context, SECI’s recent tenders discovered prices around ₹279/kg. Our illustrative case sits above it, which tells you immediately that winning bidders are assuming a lower delivered tariff, cheaper capital, better utilisation, or all three, plus incentives under the SIGHT programme.

4. Sensitivity: where the rupees are

  • Tariff −₹1/kWh (₹4.0 → ₹3.0): LCOH falls by ₹53/kg to about ₹260/kg. Nothing else comes close.
  • Specific energy +2 kWh/kg (degradation or optimistic vendor data): LCOH rises by about ₹8/kg.
  • Capacity factor 55% → 70% at the same tariff: capital and O&M per kg fall from ₹94 to about ₹74/kg, saving roughly ₹20/kg, but firming power usually costs more than that.
  • CAPEX −20%: saves about ₹19/kg (capital, O&M and stack shares together).
  • WACC 10% → 8%: CRF drops to 0.1019, saving about ₹10/kg.

The lesson for Indian developers: chasing a cheaper electrolyser matters less than securing a low, well-structured delivered power cost and a bankable offtake. Engineering effort is best spent on renewable-electrolyser sizing ratios, storage buffering, and minimising system kWh/kg, not just stack price.

5. Common mistakes in LCOH models

  • Using stack efficiency instead of system efficiency at the AC meter.
  • Using the generator PPA price instead of the landed tariff after open-access, banking and wheeling charges.
  • Assuming nameplate capacity factor without modelling the hourly renewable profile and minimum turndown.
  • Leaving out compression, storage and purification needed to meet the offtaker’s pressure and purity spec.
  • Mixing nominal tariffs with a real discount rate (or vice versa).
  • Ignoring the cost of meeting India’s Green Hydrogen Standard (≤2 kg CO₂e/kg H₂), which may limit grid top-up.

6. Try it yourself

Our free LCOH calculator runs this same framework in your browser, including a price-ceiling mode where the electrolyser only operates below a chosen tariff. Pair it with the electrolyser sizing calculator to check BoP and water quantities.

Need a bankable LCOH model for your project?

Avoltium builds techno-economic models, hourly renewable-electrolyser optimisation and FEED packages for Indian green hydrogen and green ammonia projects, backed by hands-on electrolyser development experience. If you are preparing a SECI bid, a DPR or a lender’s technical review, see our consulting services or get in touch to discuss your project.

Figures in the worked example are illustrative screening assumptions and not professional investment advice. See our disclaimer.

spot_img

latest articles

explore more