India Green Hydrogen Reality Check: Offtake to FID

India’s green hydrogen story has spent the past fortnight on two very different tracks. On one side, headline numbers: offtake commitments of more than 5.5 lakh tonnes per annum and investment pledges in the tens of thousands of crores. On the other, a report published by Business Standard on 3 November 2026 describing a sector facing a “reality check”, with many announced projects struggling to progress from MoU and allocation stage to construction.

What the report says

In summary, the report points to a widening gap between the capacity India has announced under the National Green Hydrogen Mission and the capacity actually under execution. The recurring themes are familiar to anyone working on Indian projects: delivered green hydrogen still costs well above grey hydrogen, domestic demand-side tendering has been slower than expected, and lenders remain cautious about committing to plants whose revenue depends on long-dated, sometimes non-binding, offtake. Much of the offtake celebrated recently is export-oriented ammonia and methanol, which brings its own shipping, certification and counterparty questions.

Advertisement

None of this contradicts the offtake headlines we covered last week in India’s Green Hydrogen Offtake Commitments: 2026 Update. It is the other half of the same picture: signed demand is a necessary condition for a bankable plant, not a sufficient one.

Why projects stall between allocation and FID

From our project work, the stall point is rarely a single issue. It is usually three or four unresolved items that compound:

  • Power cost and profile. Electricity is 60–75% of LCOH. Projects that sized electrolysers before locking round-the-clock (RTC) renewable supply, banking terms and open-access charges often find their capacity factor assumptions do not survive contact with the actual PPA.
  • Offtake quality. A term sheet with price review clauses, volume flexibility and no take-or-pay floor is not something a lender will underwrite against a 20-year debt tenor.
  • Technology risk on large stacks. Few vendors have multi-year operating data at 100 MW+ scale. Degradation and availability guarantees remain thin, which pushes up contingency and DSCR requirements.
  • Balance-of-plant and storage. Buffer storage, compression and water treatment are frequently under-scoped at feasibility stage, then reappear as 15–25% capex growth at FEED.

Engineering take: what Indian developers should do now

Our view at Avoltium is that the “reality check” is healthy. It separates projects that were announced from projects that were engineered. For developers holding SIGHT allocations, state land or export MoUs, four actions make the difference.

1. Optimise the power-electrolyser-storage system together, not in sequence. The cheapest kilogram rarely comes from the largest electrolyser. Co-optimising solar/wind oversizing, battery or hydrogen buffer storage and electrolyser turndown against the offtaker’s required delivery profile typically shifts LCOH more than any stack price negotiation. Ammonia synthesis in particular needs a steady hydrogen feed, so the buffer and Haber-Bosch turndown range must be designed against hourly renewable data, not annual averages.

2. Build the LCOH model lenders will actually test. Run P50 and P90 cases on generation, explicit stack replacement timing, degradation-adjusted specific energy consumption and realistic availability (93–96%, not 98%). If the project only clears its hurdle rate at P50 with optimistic SEC, it is not ready for FID. Our step-by-step method is in How to Calculate LCOH for Green Hydrogen in India.

3. Convert MoUs into bankable offtake. Push for minimum take-or-pay volumes, an indexation formula tied to identifiable cost drivers and clear certification obligations (India’s Green Hydrogen Certification Scheme plus the destination market’s rules, such as EU RFNBO or Japan’s CfD criteria). Export deals should specify who carries shipping and terminal risk.

4. Pick a phased first train. A 50–100 MW first phase with proven technology, a captive or near-captive offtaker (refinery, fertiliser unit, or steel DRI blending) and a site already selected for expansion will reach FID far faster than a 1 GW single-phase plan. It also generates the operating data that de-risks phase two financing.

Commercial outlook

We expect the next 12–18 months to see consolidation: a smaller set of well-engineered Indian projects reaching financial close, while weaker allocations lapse or get re-tendered. Domestic demand mandates for refineries and fertilisers, if notified with clear volumes and timelines, would be the single biggest accelerator, because they create offtake with creditworthy public-sector counterparties. Until then, export ammonia will carry most of the volume, and engineering discipline on power supply and storage will decide which projects make it.

Avoltium supports Indian developers with pre-feasibility, LCOH modelling, electrolyser selection and owner’s engineering. If your project is stuck between allocation and FID, talk to our team.